Thembalethu has a newly launched substation (66kV substation).

The George Municipality said the station was completed in five (5) years, at a total cost of R90 million.

About R48 million of this amount, was grant-funded by the Department of Electricity and Energy. 

The substation has modern protection, control and communication technology and a Fibre-optic cabling network which supports remote monitoring, security surveillance and substation control.

According to Michael Rhode, Director of George Municipality’s Electrotechnical Engineering Services, the project represents a major investment in bulk electricity infrastructure. 

“The infrastructure will improve electricity supply reliability to Thembalethu and enhance the municipality’s ability to manage demand across the network. It will also reduce the load on neighbouring substations in Pacaltsdorp and George Industria, helping to preserve available capacity and provide alternative supply options during system faults” said Rhode.

He also said the substation closes a much-needed 66kv ring circuit for George and brings redundancy when the network is under stress.

 Picture: Dignitaries Tour Thembalethu Substation Control Room: Executive Mayor Browen Johnson, local ward councillors, and municipal officials inspect the advanced switchgear and control room technology inside the newly commissioned Thembalethu 66kV substation.